Renovation Guide

Welcome to the RenovateDSM.com Renovation Guide!


This online "book" is intended to provide background information to people who are either exploring renovation for the first time or looking for a fresh point of view on the residential renovation process. Those who are undertaking smaller-scale projects such as a kitchen remodel, addition, or deck, may still find a lot of useful information.

This renovation guide is a work in progress much like most renovation projects! It is arranged chronologically starting with background information on renovation in general and ending with the final occupancy inspection. I suggest that anyone considering renovation for the first time read through the entire online guide from start to finish. Renovators looking for specific information can navigate to specific sections or categories of information using the table of contents.

Renovation is a very individualized activity. Not everyone will go through the same process, have the same goals, or obtain the same outcomes discussed in this booklet. With this in mind, I would like to take this opportunity to welcome you to the Wonderful World of Renovation! Despite all the warnings on the following pages, renovation is both fun, rewarding. When done right you can turn an abandoned shell of a building into a unique home that meets modern comfort and use needs while retaining its character and history.

Disclaimer and Copyright


Content will be updated regularly (or as I have time!), I would appreciate contributions from anyone with their own bits of wisdom and experience they wish to share and credit will of course be given when appropriate.

Unless otherwise noted, all text and images on this web site are copyright Steve Wilke-Shapiro. Out of respect for the time and energy that went into the creation of this online guide, I request that any use of text and/or images be approved by me beforehand. For approval, please contact fill out the RenovateDSM contact form - I'll get back to you as soon as possible.

Rules of Renovation

Renovation is a difficult and complicated process. The following “rules” can help you know what to expect and help you prepare to cope with the surprises that will eventually crop up - and they will (see rule #2).

  1. There are no rules.
    Every renovation project is different, but keep reading anyways. Having a solid foundation of general knowledge about the process can help you navigate through the rough points.

  2. Renovation projects will have surprises.
    You never know what you will find behind the plaster, under the floor, and in the eaves until you start work – there are no certainties. Sometimes the surprises are good (we have found signed notes written by the original carpenter). Other times the surprises are negative, such as substandard plumbing or rotting joists.

  3. Renovation can be stressful and usually takes longer than you first anticipate.
    Since there are no certainties, depending on things to turn out exactly as you plan results in extra stress. Anyone who tells you otherwise is probably selling something. It is generally good practice to plan in extra time and money to deal with any unanticipated problems.

  4. Renovation is complicated.
    Renovation involves many decisions and sometimes compromises to obtain the best final product. Often decisions must be made between two positive, but contradictory options.

  5. Renovation is worth the trouble.
    A renovated home represents the best of the past and the innovation of the present. With knowledgeable and experienced people on your side, good contractors, a little forgiveness, and some old-fashioned sweat equity, your project will be satisfying and worthwhile.

Intro to Project Planning

The topics discussed in this section represent decisions that will affect the entire project and should be made early in the process. Good planning is key to the overall success of the project.

This section discusses the two major early planning decisions that will most affect the outcome and timeline of the project: financial decisions and management decisions. Financial decisions include budgeting, contingency planning, and financing. Management decisions include timeframe, "sweat equity", and hiring professionals.

Keep in mind that no amount of planning will cover all contingencies, but a sound plan can help you overcome any setbacks that crop up through the process.

One of the fundamental aspects of sticking to a good plan is to start with good record keeping. I strongly suggest maintaining a three-ring binder with copies of all proposals, invoices, decisions, and research. You can also use this binder to store warranties for the fixtures, appliances, and materials in your project. At the end of the project it serves as a historical record of your process.

Taking Stock


One of the first issues that needs to be addressed is your own set of needs and desires for your home. The questions on the Programming Questionnaire page can help you figure identify these needs and wants. You will need to determine among other things:

Preliminary Financial Planning

The most difficult and stressful decisions you will have to make through this process are likely those that have to do with budgeting and financing. There is no getting around that fact that renovation is risky and can cost a lot of money. Your early financial decisions (how you will fund the project) have a large impact on later work and your ability to successfully complete the job.

Budget


Budgeting for a renovation project is closer to art than science. Anyone who has ever gone through this process knows that keeping within a budget involves making difficult decisions. The ways to spend your money are endless, but your bank account is most likely not. Your Realtor®, your lender, your design professional, your contractor, and helpful friends who have been through the process can assist you in setting realistic financial goals and fitting your ideas and goals into your budget.

If your decide to get a standard construction loan, it is likely that your lender will require a detailed budget as part of the approval process. In this case you may need to get preliminary drawings and preliminary bids from contractors prior to closing. Other loan products require you to hire a "consultant" who prepares a budget and approves construction draws as the work progresses. Even if you are financing out of pocket, a preliminary budget is indispensable.

Contingency


Your ballpark target budget should include 10-15% or more as a "contengency" fund. You will need to tap into this money when your contractor determines that you need to replace an additional six floor joists under the bathroom. Or when you find out that the windows you thought you could repaint aren’t salvageable (see rule number two).

Funding and Financing


You have many options for funding your renovation project, but make sure that you have enough money in place before you begin the project. You don’t want to be caught in situation where you have invested money in your property and cannot complete the renovation. If this happens, you are not likely to recoup your investment. Several banks offer “purchase-renovate” products and will loan you money based on the after-improved value of the property. Depending on the location and type of project, the state and federal governments both have tax-credit programs that can help defray renovation costs of properties in designated historic districts.

In certain neighborhoods in Des Moines, Neighborhood Finance Corporation has forgivable loan programs to help defray down payment and some renovation costs for owner-occupants.

Be careful that you do not agree to borrow more money than you can comfortably make payments on. Be wary of adjustable rate mortgages (ARMs), interest-only loans, and other programs that you either don't understand all the rules. This is a particularly key point for first-time homebuyers. On top of your mortgage payments, home ownership carries with it a host of additional financial requirements including (but not limited to) ongoing maintenance, insurance, taxes, sewer, water, electric, security, and gas.

Preliminary Management Decisions

It takes an especially dedicated person to live in a house while it is being renovated. If you intend to do this, you must have a minimum set of working facilities such as bathroom and kitchen in order to occupy a residence. Since most gut rehabs take between 6-12 months to acquire, finance, design, and construct, people generally prefer to maintain an alternate residence during construction.

Plan out what you will do if the project takes longer than expected, or contractors are difficult to schedule when you need them. The summer months when everyone is working on house projects are typically a contractors’ busiest.

Your Involvement


You must determine the extent to which you want to be involved in the process. Things to consider while making this decision include:

  1. How much “sweat equity” can you contribute? You can save money by doing some of the non-structural demolition yourself (plaster, non-structural walls, old wiring, old plumbing, etc). Other things that are relatively easy to learn are painting, tiling, cabinet installation, and hardware installation.
  2. Can you serve as general contractor? The general contractor gets bids for work, coordinates sub-contractors, verifies workmanship, and makes sure that work is performed per plans.
  3. What is your decision-making process?You will be expected to make numerous decisions regarding finishes such as counters, cabinets, colors, fixtures, carpet, etc. The more reading and research you do beforehand, the better equipped you will be to make informed decisions.

Working with Professionals

One of your most important decisions will be the degree to which you want to be involved in the planning and implementation of your project. It is always advisable to have an experienced professional available - whether to run the entire job or simply answer the questions you will inevitably have.

There are two people whose primary job responsibilities include helping your project run smoothly: the architect and the general contractor. Each one has specific roles, responsibilities, and liabilities. This section discusses what architects and general contractors bring to a renovation project.

There are also several other professionals you may wish to bring into your project for various reasons. If you are using Historic Tax Credits to help finance your project, particularly if you are doing the renovation as a developer, you may want to consider hiring a tax professional or accountant to advise you on how to best take advantage of the credits. If your building requires major structural renovation or remediation, you may want (or be required) to hire a structural engineer. A lawyer can assist you in negotiating contracts and preparing legal documents for condominiums, easements, evictions, and other legal needs.

Architects and Design Professionals

Not every renovation project legally requires the participation of a registered design professional.

Why Hire a Design Professional?

Architects and design professionals can provide a broad range of services that increase the finished value and make the renovation process easier.

  • Skills and Knowledge – Through education and practice, design professionals learn the ins and outs of the renovation process. A design professional can help you make sure that things get done how and when they need to be done as well as ensure that applicable building and historic codes are followed. A complete and accurate set of construction documents helps contractors estimate accurately, helps you acquire the appropriate permits, and provides you with a legal foundation if disputes arise.

  • Time Commitment – A design professional can assist you through decision-making processes and save you time in permitting, contractor selection, and construction administration.

  • Technology and Experience – Today, computer aided drafting can greatly speed the design process. Many design professionals today use CAD to produce accurate and complete construction documents in a time-efficient manner.

  • Design Talent and Idea Source – Design professionals are spatially oriented people. They became designers because they love creating interesting and unique spaces. They can help you make decisions that help increase the visual impact usability, and resale value of your home.

Design professionals and firms that focus on renovation do so because they believe that adaptive reuse of our existing building stock is key to rebuilding and maintaining a vibrant urban core.

What Does a Design Professional Do?

Architects and Design Professionals can also perform a broad range of services throughout the renovation process. Some of these include:

  • Design and Construction Documents – A design professional's primary job is design and production of construction documents for bidding, permitting and construction of your project.

  • Feasibility Study – Feasibility studies are used to give a client options or help establish direction if a client is unsure of what they want or what is possible to achieve with a project. Design professionals can perform a wide range of studies for clients that include:
    • What will need to be replaced vs. retained in a deteriorated building
    • What options are available for adding on to an existing structure
    • What type and how many residential units can be put into an existing structure

  • Tax Credit Applications – Some design professionals are experienced with the requirements, forms, and processes of application for Historic Tax Credits. If your project is located in a designated historic district and could qualify for tax credits, make sure you understand the potential implications on design and construction budget.

  • Contractor Selection – The process of selecting a contractor is as important as selecting your designer. Design professionals with experience rehabilitation work can assist with this process and help ensure that the contractor is properly qualified.

  • Construction Administration – This component of services typically includes site visits to review the progress and quality of work being done. In addition the design professional can verify that work is being preformed as indicated on the Construction Documents.

Selecting a Design Professional

In no particular order, here are some key things to look for as you select an architect for your renovation project. You should decide on the relative priority of these issues before interviewing architects.

  • Experience with your project type – Architects that focus on new commercial development may not have the specific expertise to take on a historic renovation.

  • References/Portfolio – Get suggestions from people who have been through the process before. Most architects will have a “portfolio” of projects they have participated in – feel free to ask to see it.
  • Experience in your location – Different neighborhoods have different historic codes and requirements.
  • Cost and budget – As with any service, the lowest cost option is not necessarily the best. Make sure you are comparing apples to apples when considering the services provided by two different firms. Incomplete construction documents can end up costing more in the long run if contractors are not clear on the scope of the project.
  • Personality and Working Relationship – Do you get along with the architect? How much involvement do you want in the project?
  • Design sensibility – Look at the architect’s previous work and determine if your tastes match the architect’s. How well does the architect listen to what your thoughts and concerns are?
  • Is the office in the City – Architects that live and work in the city are more likely to share your commitment to rebuilding that led you to do a rehab in the first place.

Architectural Fees

Fees for professional design services have a huge range. The methods of determining fees usually fall into two main groups: percentage of construction cost and hourly. Architects whose fees are figured as a percentage of construction cost will typically fall in the 5% to 8% range. The problem with this type of fee structure is that there is a small, though not insignificant disincentive for the architect to promote cost effective design solutions. Though the architect will bill progressively through the project, it is unlikely that there will be a "refund" at the end of construction.

The hourly rate structure, however, provides little incentive for the architect to complete the drawings in a timely manner. A good compromise is the "hourly-not-to-exceed" rate structure. The architect estimates the amount of time it will take to complete the drawings and provides the client with a "cap" on the fees. This way the Client has a good sense of how much design will cost, and is still protected from unexpected design fees.

Some architects who have significant experience in renovation projects will bid by the square foot. Such a bid will probably fall in the $1.50 to $3.00 per square foot.

Architectural Design Process

Design services are typically broken down into the following phases: predesign, schematic design, design development, and construction documents. These phases, while somewhat fluid, proceed in a relatively straight line. Larger decisions and issues that affect the project as a whole are dealt with in the initial phases and grow increasingly detailed as it progresses.

Predesign

The predesign phase is where the designer gets an overall picture of the project, both physically (through existing conditions drawings) and conceptually (through program development, schedule and budget). In order to prepare the existing conditions drawings, the designer must measure the building and input the data into a computer drafting program. Few design professionals still work solely by hand. A written "program" outlines the requirements of the project – what spaces will be needed and how they should “feel”, how the building will be used and by whom.

At the end of this phase the designer has a set of drawings in that give an accurate picture of the building as it exists and a program that both parties can refer to throughout the project to assure it is progressing as planned. The program can be (and often is) fine tuned during the schematic design phase without a large effect on the scope of architectural design work.

Schematic Design

The schematic design phase is essentially a translation of the program into drawing format. Ideas and thoughts expressed in the program are put down on paper. Scheduled progress meetings ensure that the project truly represents what the client wants. Generally, the designer prepares sketches to show several potential solutions to the program and the client selects one, combines several, and/or requests specific changes.

It is important that the larger decisions made at this stage are final because backtracking after the design development has started can mean wasted time for both the designer and the client. Also during this phase, the coordination with the appropriate government entities (Plan Review and Cultural Resources if necessary) is initiated to make sure the scheme meets their requirements.

Design Development

Design development is typically the phase where much of the work in the project is done. It is during this phase that the approved schematic design is made to work precisely in the existing building and is entered into AutoCAD or another computer aided drafting program. The issues that are dealt with in this phase include, but are not necessarily limited to:

  • structural integrity and engineering

  • room finishes
  • heating/cooling layouts
  • life safety (fire separation, egress, etc.)
  • electrical and plumbing layouts
  • accessibility (if applicable)
  • initial construction details

Construction Documents

Once the design development drawings are approved, the additional required detail is added to become construction documents. A full set of construction documents generally contains floor plans with dimensions, building elevations, details, and sections through the building at a level of specificity required for permits to be issued and work to be bid and performed by contractors.

The construction documents may also contain a “specifications” sheet. The specifications spell out minimum quality requirements for building materials, methods of installation, and certain code requirements that must be followed. For large projects, the specifications are usually written in a separate bound booklet.

By this point, all necessary groups are aware of the project scope and the permits can generally be obtained in a short amount of time.

Additional Services

Architects will also perform a broad range of additional services throughout the renovation process. Some of these include:

  • Feasibility Study – Feasibility studies are usually used to give a client options or help establish direction if a client is unsure of what they want or what is possible to achieve with a project. Architects can perform a wide range of studies for clients that include:

    • What will need to be replaced vs. retained in a deteriorated building What options are available for adding on to an existing structure

    • What type and how many residential units can be put into an existing structure
  • Tax Credit Applications – Some architects are experienced with the requirements, forms, and processes of application for Historic Rehabilitation Tax Credits.
  • Contractor Selection – The process of selecting a contractor is as important as selecting your architect. Architects experienced with rehab work can assist with this process and help ensure that the contractor is properly qualified to build your project.
  • Construction Administration – This component of architectural services typically includes site visits to review the progress and quality of work being done. In addition the architect can verify that work is being preformed as indicated and in the Construction Documents.

Construction Documents

The construction documents serve as the primary means of communication between the design professional, plan reviewer, inspectors, and contractors. They consist of a series of drawings and text that describe in detail the work to be performed on your building. The drawing and text are composed on sheets of paper, usually 24" by 36" and bound into "sets" that can be distributed to the people involved in your project. For some types of projects and in some situations, the City of Des Moines requires construction documents to be prepared and stamped by a licensed architect.

There are several types of drawings you are likely to see in a set of construction docs. This drawing set may also be referred to as contract documents or simply "CDs".

Instructions to the contractor and information for the plan reviewer is communicated graphically through the drawings and also through text description. A drawing will have symbols that denote items like toilets, exhaust fans, and electrical outlets. The text descriptions will be organized into "notes," or "keyed notes".

Plans


Plans are used to indicate horizontal relationships. A floor plan shows what your building would look like if you took a large saw and cut through the walls parallel to the floor. Some of the things shown on a floor plan include: walls, window locations, stairways, plumbing fixtures, cabinets and counters, electrical appliances and lights, outlets, and flooring. A demo plan is a special type of floor plan, specific to renovations, that indicates what needs to be removed and what needs to be protected from damage during demolition. A reflected ceiling plan shows the location of all ceiling mounted fixtures and soffits.

Your construction documents may also include a site plan to indicate exterior work such as concrete patios, parking pads, trees, shrubs, and walkways.

Elevations


Elevations are used to indicate vertical relationships. An elevation shows what your building would look like to someone standing directly in front looking straight ahead. An interior elevation is a special kind of drawing that shows cabinet layouts, wall openings, and other features that happen on walls (and therefore don't show up on the floor plans).

Details and Sections


Details and sections are close-up drawings that show exactly how individual elements should be constructed. They include specific instruction such as sizes of bolts, exact dimensions of lumber, and all materials to be used in building a specific portion of the project. Designers who have worked on similar projects to yours will have a better grasp of the details required to give the contractor a good understanding of the work that needs to be performed.

Specifications


The specifications are a text description of minimum performance and building code requirements that must be followed by the contractor. Specifications include information like the minimum compressive strength of concrete, installation of finishes, and other procedural requirements.

Description of General Contractors

A general contractor is someone you hire to coordinate a home improvement project. Although most will take on any sort of project, they are normally used for bigger projects or in cases where there are multiple projects to be completed. Traditionally general contractors will have some workers on their payroll to handle demolition, carpentry, electric, plumbing, and other basics; for everything else they will hire various subcontractors, or "subs" (the balance of subs to staff varies). Often times, they will have a relationship with certain subs that they know and trust.

What does a General Contractor Cost?


Using a general contractor instead of "subbing out" the work yourself will usually cost around 10-20% more on average. In some cases, however, it may actually cost less than doing it yourself, particularly if you don't get multiple bids when hiring subs. Often the general contractor's staff can do certain jobs for less than subs.

What are the Advantages?


There are a number of advantages to hiring a general contractor.
  • First, it makes larger, more complex projects more manageable, since you can leave many of the details to someone else (finding subs, making sure the work is done and done right, paying the sub, etc).
  • Second, experience in coordinating some of the more general aspects of projects can be very valuable (e.g. knowing which parts of a project need to happen in what order, when and how to get permits, and issues of licensing/bonding).
  • Finally, since general contractors have established relationships with certain subs, providing them with regular business, it is not uncommon for a general contractor to be quietly bumped up on the schedule of projects because they want to keep the general contractor happy.

In other words, a general contractor can make a project move faster and with less heartache for you.

Getting it Right


If you do decide to use a general contractor, interview him or her thoroughly. Be sure to check references, get multiple bids, and get a very specific itemized cost breakdown as part of the contract. It is customary to add 5-15% to a bid to cover unforeseen costs. Any use of this "contingency fund" should be formally approved by you. The best way is to use a "change order" form, so you have it in writing. Note that if you plan on getting a loan to do a major project, the lender will often require that you hire an experienced general contractor unless you can demonstrate substantial experience in the field.

There are cases where a contractor and owner disagree about the cost of a change to the project - the formal procedure for handling these is called a Change Order Request.

[This article was based on text originally written by Rick Hunter.]

General Contractor Interview Questions

You will want to gather as much information as you can from potential contractors before making your decision. The potential contractor should walk through the project with you - this is your opportunity to assess the contractor’s experience, work ethic, and personal demeanor.

  1. Make sure the contractor has the appropriate business and professional licenses and is insured. Once you have signed a contract, you should request a copy of the contractor’s “insurance binder” that lists the specific coverages for your project. Save this sheet of paper with the contract and don't lose them.

  2. Get all the contact information you can. Write down the contractor's business address, cell phone, telephone, fax, e-mail address, business license number, and truck license plate. If something goes wrong during the project, you need to be able to make contact. Before signing a contract, look up the business at the Better Business Bureau web site. Complaints lodged with the BBB should not necessarily exclude the contractor, but may lead you to ask some specific questions and/or write some additional language into a contract.
  3. Ask the contractor to describe similar projects he/she has worked on. Get two or three recent references and call them. Don’t trust photos the contractor brings as your only source of information.
  4. Make the contractor aware of any individual requirements and issues with your project. Ask if the contractor can work within whatever guidelines you set.
  5. Ask about project management. Who will be working on the job? Will there be a supervisor, superintendent or lead carpenter on site or will it be managed from a different location?
  6. Inquire about timing. How much lead-time does the contractor need to schedule your project once the contract is signed? How long does the contractor anticipate the project taking?
  7. Ask about the contractor’s bidding process. What will be included in the bid? What is specifically excluded? Do they need a full set of architectural drawings?
  8. Was the contractor on time to the meeting? Did he or she call to let you know about any delays?
  9. Ask about the contractor’s business. How many projects are completed in a year? Does the contractor have an office? How long has the contractor been in business? How many employees are there?
  10. How are complaints or differences of opinion typically resolved? Does the contractor have an established punchlist system? Does the contractor warranty his or her work? Is there an arbitration clause in the contract?
  11. Ask about payment. How much money does the contractor require up front? What is the payment schedule? Can the contractor agree to the lender’s terms and the required draw schedule?

Technorati Profile

Project Management

As the owner of a building under renovation, you have to decide how much day-to-day control you want to have in the process. It is particularly natural for someone who is new to the renovation process to adopt a lassaiz-faire approach. There is a whole new language to learn, and it can be difficult and intimidating to question a contractor or design professional until you truly understand an issue.

It is important to keep in mind that it is your money paying for the job and you are the one who will have to live with the finished product! You will still need to be involved in resolving the inevitable questions that crop up - from paint selection to quality control, the buck stops with you.

This section covers some of the key management tools you have at your disposal.

Doing Things by the Book - Get Those Permits!

Many people view preparing drawings and getting permits as an unnecessary burden imposed in an authoritarian manner. Everyone involved in the construction industry has heard horror stories of overzealous inspectors that simply can't be pleased. I am asked regularly by clients to commiserate on the needless headaches inspired by the permitting and inspection process.

In select cases, I agree. Sometimes I see people put through the wringer over a relatively minor issue. However, for the most part I understand that building codes, permitting, and inspections serve a vital and important purpose. Most people actually do have problems judging for themselves what is safe and what is not, and reaching beyond one's level of expertise can have fatal consequences. Perhaps someone who leans towards an individualist philosophy could make a case that we should all have the right to be as unsafe as we see fit. The problem comes in when one person's unsafe actions begin to impact the rest of us.

Building codes are not just designed to protect unsafe people from themselves but also to protect the general public: fire fighters, future occupants, next door neighbors . Those people, who don't have any control over someone else's building, can be killed in a fire or structural collapse they had nothing to do with - building codes aim to protect them. Cities are better off as a whole when we can expect that ALL of our buildings meet certain safety requirements.

Here is the extreme case: I have been in a house with an illegal basement "bedroom" that was wired with extension cords spliced together. Not only was the "wiring" exposed, incorrectly sized, and certainly drawing more power than allowed, but adequate exits did not exist. In the case of a fire, the young child that had obviously lived down there would most likely have been toast.

That's a far cry from installing a new outlet, but I would rather fall on the side of safety.

Lien Waivers - Don't Pay Twice!

Consider the following situation: You hire a general contractor to renovate your kitchen and as part of the work, your contractor subcontracts with a plumber to relocate the sink. When you receive a bill from the contractor, you assume that the plumber is subsequently paid. However, if the general contractor neglects to pay the plumber, the plumber (or any subcontractor or supplier in the same situation) can file a "lien" against your property for the amount owed.

Such a lien is charged against the future sale of the property and you cannot transfer title until the lien is paid. Therefore you could be forced to pay for the plumbing work twice: once to the contractor, and once to the plumber.

A "lien waiver" is a document that helps ensure you will not be forced to pay twice for work performed on your property. Many lenders require signed lien waivers from all subcontractors before they will release funds to the contractor. In general, this is a good idea because it ensures that everyone has been paid what they think they are owed.

If you are paying for the work out of pocket, you may request a signed lien waiver before you write your check. In general terms, a lien waiver should include the following information:

  • Name of the company,
  • Address where work was performed,
  • Description of the service performed,
  • Statement to the effect that all subcontractors and suppliers have been paid,
  • Amount paid, and
  • Notice that in consideration of the sum paid the contractor or subcontractor releases any and all claim or right to lien on the property on account of labor or materials .

This language may take several forms, so if you are concerned about its enforceability in your situation, you should have a lawyer take a look at it.

Most lenders require borrowers to purchase "title insurance" to protect against unknown liens against the property you are purchasing. Liens may be discovered during a title search and can jeopardize your closing if not taken care of appropriately.

Negotiating a Change Order

In many cases (and for a variety of reasons) an owner or contractor may want to deviate from the architectural drawings. Some common reasons include discovery of an unforeseen condition, availability of certain products or materials, design changes, and feasibility. In some cases this deviation will cost additional money due to increased time or materials cost to the contractor. It is also possible that the change will result in a savings to the owner.

Whatever the case, when changes to the contract amount need to be negotiated there is potential for disagreements to arise between the contractor and owner. As with any interaction where both sides have legitimate claim to some portion of the truth, a peaceful resolution is all in the approach.

Keep the following things in mind as you seek a positive resolution:

  1. Be Fair - As the owner, you have to approach the issue with the honest willingness to pay for reasonable work outside the scope of the existing contract. The contractor should approach the negotiation with the honest understanding that the client is entitled to ask for reasonable backup to support any additional cost. Make sure you are negotiating in good faith.

  2. Know Your LimitsYou have to decide how far you want to push the issue if it looks like it will get nasty. Either party could end up in small claims court and the contractor could potentially place a lien on the property, wasting everyone's time, money, and sanity. Figure out what your threshold is before you start - you don't want to get dragged into something serious by accident.
  3. Maintain LeverageAssuming that the owner has not yet paid for the full contract (keeping some sort of retainage), each party has some leverage over the other - the owner wants the project done for a reasonable amount and the contractor wants to get paid. Both partis have significant incentive to work together towards a mutually acceptable solution.

The Official Request

It is reasonable for the owner to ask (nicely) for a written description of any change to the architectural drawings and a written summary of how the contractor arrived at the additional amount. In contractor-speak, this is a "Change Order Request", or COR. The COR should include a description of the discovered conditions, proposed remedy, and the proposed cost including overhead and profit. The owner may want to ask for a breakdown of time and materials for the proposed remedy. He or she can then sit down with the original contract, the architectural drawings, and of course the existing work to decide whether the proposed work should be covered under the contract or is truly above and beyond. The architect may also be of some assistance in evaluating the validity of the COR (perhaps an hour of time would be worth the expense).

Asking for an explanation of the costs in writing will often inspire a contractor to be reasonable in his or her requests. There is obviously a gray area when it comes to interpreting the results of this query. You can run to Lowes to check the proce of a 2x10, but who determines whether a time estimate is "reasonable"?

Some things to look for:

  1. Is the proposed work obviously covered in the contract in the drawings? If so, the owner is in a good position to (nicely) reject the request for additional payment. Do so in a personal conversation with a set of the construction documents. Be prepared to throw the contractor a bone in order to facilitate moving beyond the conflict - for example, offer to split the materials cost but not labor, offer to extend the length of the contract for a reasonable amount of time to complete the unanticipated work, etc...

  2. Are the materials in the proposed work obviously inflated? If in doubt, call up suppliers to verify big ticket item prices quoted by contractors.
  3. If materials are vastly inflated, take the labor estimate with a grain of salt.
  4. If the proposal is within reasonable bounds and supported by the drawings and the conditions, accept it and move on.

The owner don't want the contractor to walk off the job or to cut corners because he or she is angry and/or losing money on the job. The contractor doesn't want the owner telling 1000 other renovators about his or her bad experience. The key will be open communication and the impression that both sides are honestly working towards an agreeable solution.

Neither side wants to end up in court, but that could be a potential last resort if an agreement can't be reached. Litigation will likely extend the project timeline.

Renovation Timeline

The phases of a renovation project occur in a specific, yet somewhat fluid, sequence. If a component happens out of order, it can potentially result in significant costs - both time and money. For example, say you schedule your electrical contractor before your HVAC contractor. The electrician may unintentionally run wiring through a joist cavity that will later be necessary for a heating duct. This will result in either calling the electrician back or finding another (potentially more expensive) route for the duct - it is much easier for the electrician to adjust where wires are run than for the heating and cooling contractor to adjust where ducts are placed.

If you hire a general contractor, he or she will take responsibility for scheduling issues and minimize any conflict between the subcontractor trades.

The graphic timeline to the right shows the general order of a gut renovation project from financing through move-in. Remember, of course, that each project is individual – not every renovation will include all these phases (and some will include more). Some people experienced in renovation may have systems and procedures that differ from what you see here. However as a general rule, bigger and more independent tasks are completed before detailed and flexible tasks. Arrows indicate the length of the phase and arrows that overlap indicate phases that can typically occur concurrently.

Click on the image to the right or on the link below to download a readable (and printable) PDF version of the graphic renovation timeline.

Financing and Budgeting

The Bad News


First the bad news: There are no no two ways about it, renovating a house is expensive in both time and money. There are a huge number of variables in determining how much a specific project will cost in the end. It is therefore impossible to create a "rule of thumb" for cost estimating without individually inspecting the specific property.

Depending on the following conditions, gut renovations generally cost anywhere between $40 per square foot and $140 per square foot. The big variables are, in no particular order:

  • General Condition - With some exceptions to the rule, the worse physical condition the property is in, the more it will cost to bring it up to a finished state.
  • Sweat Equity – Hiring a contractor is more expensive than doing work yourself.
  • Finish Level – Granite counters are more expensive than laminate. Tile is more expensive than vinyl flooring.
  • Kitchens and Bathrooms – These are the most expensive spaces per square foot.
  • Structural – Fire and water damaged structures are relatively expensive to repair.
  • Masonry – Rebuilding walls and tuckpointing are relatively expensive.
  • Siding - Worn vinyl siding is difficult to repair. Deteriorated siding should be replaced with like material. The more extensive the damage the more it will cost. At some point it makes sense to simply reside the whole structure.
  • Custom Restoration – Historic features like carved wood handrails and plaster crown molding are difficult and expensive to restore or replicate.

The Good News


Here’s the good news: there are plenty of people out there who want to help you finance your project if you have decent to good credit. Banks continually improve their loan products to take advantage of the purchase-rehab market.

There are several banks and lending institutions in Des Moines that have renovation loan products. Neighborhood Finance Corporation targets certain geographic areas with forgivable repair loans and down payment assistance. These forgivable loans are not income tested - anyone who purchases a house in an eligible area may qualify.

A so-called "purchase-rehab" loan (a 203k loan is one example) may help bridge the gap between what a house is worth before renovation and what it is expected to be worth when the work is complete. The loan amount is based on the estimated after-improved value of the property. Money for renovation is put in an escrow account and released to contractors as they complete work. Some purchase-renovate loans require additional paperwork throughout the renovation process. Make sure you understand the inspection, paperwork, escrow, and payout requirements!

The Finer Points


Interest rates are typically higher on all types of construction loans. Renovators usually finance the renovation with a purchase-renovate loan or a construction loan and then refinance into a fixed or ARM with a lower interest rate. Often certain components of the renovation (a third floor for example) can be put off until after refinancing - the equity (hopefully) developed through the renovation can be leveraged to finance additional work.

If your property is located within a designated historic district, your project may qualify for historic tax credits. The tax credit application is certainly not rocket science, but it does require significant effort and may prove frustrating for people who are unfamiliar with the process. There are people who specialize in preparation of historic tax credit applications for a fee. Your architect or design professional may also provide this service.

Budgeting


Many lenders will require a professionally prepared set of architectural drawings as part of the loan-making process. These drawings help the lender establish the estimated after-improved value of the property and help the owner get comparable bids from contractors. See the section about Design Professionals for additional information.

You should by this time, through the lending qualification process, have a good understanding of your own finances and how much money you will have available to you for the renovation project. Some loan products will require the participation of an inspector to assess the building and your plans to put together a preliminary general budget.

If you are managing the project yourself (serving as your own general contractor) and getting a conventional construction loan, you will need to prepare a much more detailed budget. It helps to have a contractor available to bounce numbers off of. A design professional may also have some advice for this stage. The RenovateDSM construction estimate worksheet can assist you in tracking your budget numbers and helping to make sure you don't miss any major categories.

Make sure you include a healthy contingency number between 10 and 20 percent depending on the scope of the project and you own construction budgeting experience.

Construction Estimate Worksheet

This spreadsheet was developed to assist in the cost estimating and budgeting phase of a renovation project. If there is additional information you think should be included on this spreadsheet, or if you have other questions, please fill out the Contact Form.

Download this file by clicking on the link below.

Finding the Right Building

Sources of Property

The primary sources for property acquisition are: private individuals, private corporations, city government, and the federal government. Private property is sometimes listed for sale through a licensed Realtor® and available for purchase by the general public. Many of these buildings, while requiring either renovation or updating, have been recently occupied and are in reasonably good physical condition. When purchasing a private individual residence, make sure that your purchase price accurately accounts for the money you will be investing in its renovation. Your bank will help ensure you don’t dump more money in than the house will be worth, but remember that they are also interested in selling you a loan. Don't be afraid to reject a building if the "numbers" don't work for you.

Sometimes, privately owned unoccupied property has been left abandoned for years and is in poor physical condition. These buildings are generally boarded up and not listed for sale by a Realtor®. The owners may also be difficult to track down, particularly in cases where he or she lives out of state or has moved repeatedly. The Polk County Assessor web site can help track down the owner of a particular building.

The Department of Housing and Urban Development may have property for sale. Teachers and police officers may purchase properties in specific zip codes at half price.

Owner Occupants

If you will be renovating the house to live in yourself, you should also spend some time and effort looking deeper into the "quality of life" in the surrounding neighborhood in addition to the economics of the project. Bottom line: is this a place you see yourself being happy living 24 hours a day? If you have children, you may be particularly interested in researching things like the neighborhood schools, parks, and nearby child-friendly restaurants.

Talk to members of the neighborhood association about the benefits and tradeoffs of living in the area.

Building Assessment Basics

Within the confines of this brief summary, it is impossible to tackle all the issues you should examine in a potential property. Make sure that you have trustworthy and knowledgeable people available to give you advice before buying a house. While this is always important, it is particularly crucial with a renovation – you and your lender are taking a greater risk buying a property “as-is” and sellers are less willing to include correcting problems as part of the price negotiation. Some people you may want to have examine a house before you put in an offer include:

  • Realtor® – sound advice on price and potential appreciation

  • Architect – discuss potential design, space, and structural issues
  • Structural Engineer – determine severity and remediation of structural damage if any is noted
  • Independent Inspector – provide background on potential code and safety issues
  • Environmental – test for presence of lead paint or asbestos
  • Independent Appraiser – how much will the house to be worth after rehab

What to Look For

The average person can quickly assess some basic structural conditions and determine if professional advice is required:

  • Brick Masonry – Look for large sections of missing mortar, missing or cracked brick, and bulges in the exterior walls. Check for cracks around openings (windows and doors) and misshapen (squashed) brick arches. On the inside, look for areas of discolored plaster along the exterior walls that may indicate water leakage

  • Siding - Examine wall/roof intersections, corners, window trim, and architectural details (brackets for example) for indications of rot. Look for cracked or peeling paint that may indicate water damage.
  • Foundation – Examine limestone or concrete block foundation walls for missing and/or loose mortar. Minor cracks in the foundation may be a function of acceptable settling – they can be filled. Large cracks need to be examined by a professional.
  • Plaster – Small diagonal cracks around doors and windows can happen over time as the house settles. These can usually be patched. Large areas of cracked, damaged or sagging plaster may need to be replaced and may indicate underlying structural issues that need to be corrected. Areas of discolored plaster may indicate water leakage through the roof or adjacent wall.
  • Fire Damage – A professional should assess any fire-damaged portion of the building. Some indications of fire damage include black char marks outside windows, soot stains on walls and ceilings, exposed charred joists, missing sections of roof and significant water damage in only one portion of the building.
  • Water Damage – Long-term exposure to ice and water can severely compromise a building’s structural integrity. Look for areas where the floorboards are coming up, where the roof is missing or damaged, plaster has fallen to the floor, the joists and/or floorboards have significant “give” or areas of visible mold and mildew. Do not walk on any questionable area.
  • Beams and Joists – Examine the beams and joists in the basement for large cracks, areas of rot or mildew, missing posts, and large sags.

Each of the above issues may result in rebuilding or removing a portion of the structure. If you think that the building may have one or more of these problems, contact a professional. If structural remediation is required, be prepared for it to take a significant amount of time and/or money.

Sometimes, the building systems have been stripped out of abandoned buildings for resale, reuse, or scrap metal. If furnaces, electrical wiring, and plumbing remain, you will need to assess their condition and determine what, if anything, can be saved.

Plumbing

Look for missing sections of copper supply line in the basement, lead pipe coming into the residence from the water main, and any areas of obvious water damage caused by leaking pipes. Areas of cracking concrete in the basement may indicate a collapsed cast iron sewer line as may sinkholes in the back yard. If you are making changes to the plumbing fixtures in the bathrooms and kitchen, you will probably need to install a new waste stack and vent. Your plumber may be able to tie in to the existing sewer line - he or she can "camera" the sewer to determine its exact condition.

Electric

Fuse boxes, knob-and-tube wiring should be upgraded to at least 100 amp service (possibly 200 amp depending on the size and load requirements). Substantial renovations may require a complete rewire to conform to current codes. Some insurance companies will decline to cover buildings with knob-and-tube wiring. It is not inherently unsafe - in fact the hot and neutral wires are completely separated. As long as the wiring is not disturbed (which may degrade the insulation) you shouldn't feel particularly unsafe in a home with K&T wiring. The main problems are that there is no ground wire and the wiring itself may be undersized for modern electrical loads.

HVAC

If the gas and electric service are connected, adjust the thermostats to turn the HVAC units on to test them. Look for evidence of leaking at all radiators. If there is a forced-air unit verify that air gets to the furthest ducts and is an appropriate temperature. Keep in mind that if you want to change the floor plan as part of your renovation, it may require alterations in the HVAC system (size or duct layout).

Securing the Building

Expensive tools and supplies are often stored in buildings under renovation. The combination of an empty building, signs of renovation (such as a roll-off dumpster) and things of value stored inside can make renovations tempting targets for thieves. Additionally, some buildings in poor physical condition may be in danger of further deterioration unless effort is made immediately to deal with water infiltration or other structural damage.

Accordingly, the first thing you want to do after closing is to secure the building. Depending on the condition of the building you purchased, securing it can be a significant component of the project and can include the following:

  • Structural stabilization – If the building has sustained fire or water damage, assess the stability of the structure. Stabilization may consist of building temporary interior walls to support damaged floor joists or rebuilding exterior brick walls that are bowing out. If you are unsure of the structural condition, seek the advice of an engineer.

  • Keeping out the elements – Water is the enemy of renovation. Secure heavy-grade plastic over roof leaks and board up broken windows/doors.
  • Security – Go directly from closing to the house and change the locks. You have no way of know who has keys to your new property, and you are now responsible for it.
  • Make the property less desirable – The dumpster out front and the permit in the window will let everyone know that the property is under construction. Remove and store elements that may attract thieves such as mantles, light fixtures and appliances you want to retain. Do not store valuable tools on the premises. Make a show each evening of removing your tools. If you have electric power available, you may want to consider having an alarm company install a temporary alarm to help prevent break-ins.
  • Insurance - If your homeowner’s insurance does not cover construction, obtain a temporary rider or separate policy to cover any catastrophic loss.

As part of the securing process, if the building does not have electric service, contract with an electrician to install either temporary service or upgrade the service and install a “construction” outlet on the breaker box. Having electricity available will allow for easier construction work as well as the installation of a temporary security system.

Renovation Design

If you intend on hiring a design professional to prepare drawings for your renovation project, you should hire this person as early in the process as possible. Some design professionals will be willing to assist in evaluating potential properties, but others prefer to wait until you have a property under contract before committing their time.

Not all renovation projects require professionally prepared drawings. However, a design professional provides more than just drafting skills. The design professinal’s job is to help you through the daunting and sometimes frustrating decision-making process by suggesting proposed solutions and providing insight into potential problems. This is why the one you select should be experienced in your type of renovation project - ask for references and a portfolio of similar projects. There are issues specific to renovation that an design professional who specializes in commercial construction will not necessarily be familiar with.

Your design professional's work is not done when the drawings are complete. He or she should be available to answer questions from contractors and sub-contractors during construction. You can also retain his or her professional services to assist in finish selection (faucets, paint colors, etc) and construction administration to help ensure that the project is built according to the plans and specifications.

Design services are generally divided into the following phases: pre-design, schematic design, design development, and construction documents. These phases, while somewhat fluid, proceed in a relatively straight line. Larger decisions and issues that affect the project as a whole are dealt with in the initial phases and grow increasingly detailed as it progresses.

For more information on the phases of the design process, visit the following RenovateDSM pages:

  • Design process - This section goes into detail about what to expect from each of the phases in the design process.

  • Construction documents - This page goes into greater detail about the drawings a design professional produces.
  • Design professionals - This page discussion what a design professional does and how to work with one.

Contractors and Subs

At some point during the architectural design process, it will be time to start locating a general contractor and/or subcontractors to perform required work. By this time, you should have already decided whether you will serve as general contractor or hire a general contractor to manage the project. If you are hiring a general contractor, there are two approaches.

Selecting a Contractor

The first approach is to find a trusted general contractor to work with you through the design process. Allowing the general contractor to have input in the budgeting and design process and may lead to savings if he or she can suggest alternate materials and details early in the process. There will also be a time savings because you won't have to wait for multiple contractors to bid the project from the completed construction documents. However, you have to really trust the contractor to be fair in pricing. If the contractor knows your budget, it's likely that the project will end up costing that amount!

The second approach is to competitively bid the project to two or more contractors. This approach requires you to have a complete set of construction documents to ensure you are comparing equivalent scopes of work. If different contractors are making different assumptions, you will be unable to compare the bids side-by-side. It is not necessarily appropriate to take the lowest bid - you make sure that the bid you accept is including all the work you want done and that the quality of work will be acceptable.

Locating contractors and subcontractors involves:

  1. Get recommendations from friends or other trusted sources.

  2. Contact companies and arrange times to meet potential contractors at the house for a walkthrough. If you take a day to meet multiple contractors, schedule them with enough time so that contractors from the same trades do not overlap.
  3. Compare bids side-by-side and ask for clarification if necessary. Be aware of vague language and get all dates in writing. Make sure you get along with the contractor and do not have any immediate communication problems.

Your architect can assist in the contractor selection process by providing preliminary drawings, evaluating bids, and answering questions.

License and Proof of Insurance, Please

Verify that all contractors you work with are licensed and insured for your project. Insurance covers injury to workers on site and damage to property caused by the contractor – your homeowner’s insurance policy may not appropriate coverage for construction. You may request that the contractor furnish you with a "certificate of insurance". This certificate should be faxed or mailed directly from the insurance company and reference your specific name and address. Do not accept any other proof of insurance.

Beware of Liens

A lien is a legal encumbrance on the deed to a property ensuring that it cannot change hands until the lien holder is paid. As you make payments to your contractors throughout the construction process, always request signed lien wavers. If you are working with a general contractor, ask for signed lien waivers from all subcontractors before releasing the final payment. The lien waiver ensures that you cannot be “double-billed” for services. For example, consider a draw payment submitted by the general contractor that includes the electrical rough-in. You pay the general contractor and assume that the electrician gets paid subsequently. However, if for some reason the electrician does not receive the money owed, he or she can place a lien against your property for that amount. In order to release the lien you could end up paying for the same work twice.

Selective Demolition

This phase encompasses the removal of all existing building materials that you intend to replace or that block access to other components of the project. If you are altering the building’s structure, it will be necessary to construct temporary supports to prevent damage to the remaining structure. Consult a professional if you are unsure of which elements are structural and which may be safely removed. Selective demolition drawings are required as part of the construction documents you present when you get your permit.

Before demolition starts, you or your contractor will need to contract with a private "roll-off" dumpster service – most dumpster services rent their dumpsters at a specific weekly rate and add either a collection fee or a “per ton” fee for dumping. Purchase a tarp to cover the dumpster and prevent rainwater from soaking the materials, which will add significant weight.

Demolition is one area of skills that is easy to acquire and will help you to gain a better understanding of the way your house is built. However, some demolition activities may require special preparation to reduce potential danger:

  • Hazardous materials – It is important to have the building assessed for environmentally hazardous materials such as lead paint and asbestos. If these materials are found you may either have them professionally removed or “encapsulated”.

  • Structural walls and beams - Your architectural drawings will indicate which walls are load bearing. Do not attempt to remove walls or cut beams without professional advice and/or assistance. Be particularly careful working with any wall that runs perpendicular to the joists above.
  • Decks and porches - If you are removing a wood deck or porch, be very careful to prevent a collapse. Avoid standing on or under any destabilized structure as you are working.
  • Damaged floors and joists - Pay particular attention to the floor structure (subfloor and joists). Water and fire can compromise the floor's structural integrity, adding to the danger for an inexperienced worker.
  • Roof - The higher you are off the ground, the greater likelihood a fall will cause serious harm. Sloped roofs can be dangerous if shingles are in poor condition (slate roofs are even higher risk of failed connections and slippery situations). Leave the high-wire acts to the professionals.

The following demo activities fall within the skill range of most people.

  • Carpet - Most carpet is attached to the floor beneath with a “tack strip” around the edges. Start at one corner and pry the edge of the carpet up from the tack strip. Once one corner is released, the rest should come up with a strong tug. Use a thin pry bar to remove the tack strips after the carpet is pulled. Use needle-nosed or "nail-biter" type pliers to remove any staples and carpet tacks.

  • Trim, casing, and moldings - Use a thin pry-bar as a lever against the wall - try to pry where nails are located to minimize cracks and splits in the wood. Attempt to work slowly and evenly across the length of the piece rather than prying one side completely out before the other. Using pliers, pull nails out through the back of the wood. Store architectural woodwork in a dry, safe location during demolition and construction.
  • Plaster - Plaster is held to the walls and ceilings on thin pieces of wood called lath. It is relatively difficult to remove small sections of plaster/lath without damaging the surrounding area. Large areas, however can be removed quickly using a few simple tools including a hammer, medium or large crowbar, and sledgehammer. Be careful of exposed nails in the lath that comes off the wall and always wear appropriate gloves, breathing masks, long sleeves, and long pants. Some plaster may contain asbestos fibers and paint may contain lead. If you suspect any hazardous materials, hire a licensed contractor to assess and remove them.
  • Cabinets and fixtures - Permanent “furniture” such as kitchen cabinets can usually be easily removed using a cordless screwdriver and pry bar. Most fixtures such as toilets, sinks, and tubs can also be removed easily after shutting off the water supply. Cast iron tubs that are in unsalvageable condition can be broken up using a sledgehammer and removed in pieces (wear safety glasses and protective clothing to prevent injury from flying shards) - this is a good way to release some of your pent-up frustration over financing, permitting, and design.

Performing some of the demolition yourself can help ensure that items you want saved are protected appropriately. Participating in the selective demolition process can help give you a better understanding of historic construction practices. If you hire a demolition contractor, be very specific about the architectural features you want protected (windows, railings, trim, fixtures, doors, fireplace surrounds, etc.) and the walls to remain. You may want to build temporary protection out of plywood around large items to remain, such as a carved railing or a built-in stone fireplace surround.

Roofing

The roof serves as your home’s primary barrier to rain and snow - keeping water out of your home is particularly important during construction. Water is an enemy of most construction materials and trapped moisture can encourage growth of mold.

If possible plan for any future penetrations through the roof prior to installing or repairing an existing roof. It is always more work and less effective to retrofit penetrations through an existing shingle or membrane roofing installation. Some examples of potential penetrations include chimneys, flues, roof vents, plumbing stacks, and skylights.

Roof Types

There are three primary types of roofing found on homes in Des Moines: single-ply membrane (flat), built-up (flat), and the most common being shingle/tile (sloped). Some buildings have combination roofs with a sloped roof in front and a flat roof in the back.

Built-up roofing (BUR) is a generic term for any roof that is built with multiple layers on a flat roof. A BUR system typically has layers of “felt” or other membrane alternated with layers of tar/bitumen. The top layer is usually a stone aggregate spread over the entire surface. This roofing type is more typically found on commercial buildings.

A single-ply membrane (SPM) roofing system consists of a single layer of waterproof sheeting. The SPM material comes in large rolls, and can be fastened in a number of ways to the substrate on a flat roof. Its ease of installation makes SPM systems relatively inexpensive.

Asphalt shingles are the most common roofing system on sloped roofs. Shingles are mechanically fastened (nailed) to the roof’s substrate. A layer of roofing felt between the shingles and the substrate helps provide a waterproof barrier. In general, shingles may be installed over existing shingles up to three layers deep. All layers must be removed prior to the subsequent installation - this is also a good time to make any required repairs to the roof sheathing. If your building has existing slate shingles that cannot be repaired, they should be removed before installing asphalt shingles.

Insulation

Roof rafters and trusses must be insulated to prevent heat loss in the winter and heat gain in the hot Iowa summers. In fact, the roof is one of the primary means of heat transfer to and from your home. The two most common means of insulating the roof are fiberglass batts and blown insulation. Fiberglass batts come in either large rolls or pre-cut lengths that are placed between rafters or studs. Batts are typically installed before drywall and after electric rough-in. Blown insulation consists of fibers (often recycled material) and a fire retarder. It is spread evenly using a blower that may be rented. It is important to use enough to get the required thickness for the desired insulation value.

Resistance to heat flow is indicated with an “R-value”. The higher this number, the more insulation is provided. Insulating the roof to as much as possible will result in significant energy savings.

In some cases, if the underside of the roof sheathing is exposed, it is possible to install expanding foam insulation such as Icynene. This type of insulation is very efficient (high R-value) and serves double duty as a vapor barrier but requires professional installation.

Framing and Rough Carpentry

The building is now secured and watertight. All the required demolition has been accomplished. It is now time to take the next step towards your new home. Framing is the first of the “rough” stages in a renovation. The framing and rough carpentry set the stage for all subsequent work - this is the phase where new walls are built and any structural changes are implemented.

Since carpenters are relatively expensive per hour, you may want to minimize the “non-skilled” labor they perform. If you are serving as general contractor, you may be able to save some money by helping the carpenters distribute the supplies when they are delivered. Even a moderate renovation with some alteration of walls may require upwards of 200 2x4’x to be piled throughout the house. Particularly if the project involves furring out walls, distributing lumber will require a large amount of labor. Before the new walls can be built, it is important that all extraneous debris is cleared out of the building. You probably don’t want to pay a carpenter to move piles of lath and old carpet to the dumpster.

Framing and the Trades

The plumber and HVAC contractors must have space within the walls and ceilings to run the supply lines, return (drain) lines, ducts, and vents. Building codes and structural requirements restrict how and where they can install systems, so it may be necessary to build soffits and chases (false ceilings and walls) around drains or vents that protrude into living spaces. Careful planning and special construction methods can minimize the effects of soffits and chases. The carpenter may frame the soffits and chases before or after the building systems are installed. If they are framed before, you must carefully coordinate so there is enough space inside. Also be aware that if you are applying for historic tax credits, building soffits and chases may negatively impact application. Make sure to get approval from the reviewer prior to building any soffits or visible chases.

If you have removed the plaster on the ceilings and intend to finish with drywall, now is the time to assess the joists for any high or low points. If you find significant variation across several joists, your carpenter can attach 2x4’s, cut and bend the studs, or install shims to provide a level surface for drywall installation.

Furring Out Masonry Walls

"Furring out" is the process of building a wall inside another wall. In renovations, this often takes the form of a new 2x4 stud wall built adjacent to an existing exterior masonry wall (see photo). Furring out allows for HVAC, plumbing, and electrical systems to be run easily and also for insulation to be added to increase energy efficiency. Carefully consider the following implications as you are deciding whether to fur out the walls in your project:

  1. You will need to drywall the new wall (even if the plaster on the existing exterior wall is in good condition)

  2. You will need to install new window sills and casings because the new wall is thicker than the existing
  3. You will need to remove and reinstall all the base moldings and trim
  4. The room will be made smaller
  5. You may need to move doors, switches, radiators, or other elements that are too close to the existing walls

Benefits include better energy efficiency, ease of installing new systems, you can provide a new flat wall surface, and you can cover damaged plaster easily. Carefully weigh the costs versus the benefits.

See also the article on vapor barriers.

Building Systems

Heating/cooling (HVAC), electric, and plumbing are generally considered the "major" building systems. Related systems include, but are not limited to the following:

  • HVAC

    • Whole house vacuum system

    • Humidifier and dehumidifier
    • Mechanical venting (attic vents, bathroom vents)
    • Radiant heating
    • Make-up air
  • Electric
    • Security system

    • Backup generator
    • Solar cells
    • Low voltage systems (undercabinet lighting, telephone, intercom)
    • Cable/satellite
    • Speaker wiring
    • Structured wiring (Cat-5)
  • Plumbing
    • Radiant heat

    • Water softener or water filter
    • Swimming pool
    • Irrigation

Systems installation usually starts after framing is substantially complete. In many cases outside utilities work (sewer, electric service upgrades, and water service) is completed while framing is underway.

It is vitally important to consider the order in which systems are installed - misfiguring could result in conflicts between the trades that require work to be torn out and redone. IN general, installation starts with HVAC, then plumbing, and finishes with electric. Some circumstances may result in this chain of events being altered.

Vapor Barriers

Confusing Terms

Even professionals often confuse the term "vapor barrier" with the term "moisture barrier". Here is the difference:

  • Moisture Barrier - Moisture barriers (like Tyvek, for example) are properly installed on the exterior of a frame wall, directly on top of the sheathing, and under the siding. Moisture barriers help prevent water from entering the wall cavity.

  • Vapor Barrier - Vapor barriers, typically a polyethylene plastic sheeting, are installed on the inside of a frame wall between the studs and the drywall. Vapor barriers help prevent water vapor from the interior of the house filtering through the wall and condensing on the warm side of the insulation. Wet insulation is a no-no.

Vapor barriers are also installed under basement slabs to prevent water and ground gasses (such as radon) from making their way through the concrete.

The point of having a moisture barrier like Tyvek outside the sheathing and the polyethylene vapor barrier inside the insulation is that in the event of condensation or infiltration of vapor into the wall system, the housewrap allows moisture to escape to the outside. Housewrap will also reduce the infiltration of water and water vapor into the wall system from the exterior, minimizing the potential for water to condense at the vapor barrier.

In order to be effective, both moisture barriers and vapor barriers must be properly installed and sealed at all penetrations and seams.

Should I Install a Vapor Barrier?

If you live in Des Moines, the answer is probably yes. If you have any questions, you should consult a knowledgeable building professional. A vapor barrier will decrease air and moisture infiltration into your rooms and make your home more energy efficient.

If you are working with an existing frame wall or masonry veneer wall, there are additional considerations you should think through before deciding one way or another.

Water condenses on the warm side of a barrier. There is sometimes a concern in regards to installing a vapor barrier with a masonry veneer wall. This concern is related to the situation where, on a sunny day, water that is trapped in the brick may have a tendency to migrate into the wall system. When this water vapor contacts the vapor barrier (and the house is air conditioned - cool), it may have a tendency to condense and potentially collect in the wall system.

If you are concerned about moisture condensing in a frame wall with a masonry veneer, there are three potential solutions.

  • Don't install the vapor barrier. This will allow moisture to continue to migrate through the wall system without getting "trapped" at any one point. Downside is that this solution is not as thermally efficient.

  • Increase the air space at the brick veneer. Additional air space (say 2" instead of 1") will allow for more air flow up and out of the wall cavity, lessening the potential for water vapor to be stuck in the system. Current masonry standards call for an increased air space anyways. The downside is that if you are building a new foundation, the width may have to be increased for the additional air space.
  • Expanded foam insulation. The closed cell expanded foam insulations are also vapor barriers. Water will not migrate into or through the insulation, so you don't have to worry about condensation at the interior wall surface. Downside is that it may be more expensive than standard fiberglass batt or blown-in cellulose insulation.

Other Considerations

A properly installed polyethylene vapor barrier can create a very "tight" building envelope with little air infiltration. While this is great for energy efficiency, it then becomes important consider interior air quality. Particularly in situations where appliances, utilities, and fireplaces may be powered by natural gas, maintaining an adequate fresh air supply is critical to a healthy internal environment.

A tightly sealed home requires mechanical venting and make-up air supply to maintain healthy internal air quality.

For more information and related resource links, visit:

Heating and Cooling

In a typical household, heating and cooling make up well over half of the total energy use. Insulation and sealing up the "building envelope" from outside air can drastically reduce energy consumption. Next in line should be selecting energy efficient appliances and heating/cooling units.

Many older homes come equipped with radiator heat and an older gas-fired boiler, but no air conditioning. Chances are, you will be either upgrading or replacing the HVAC system(s) in your renovation.

Efficiency

Great strides have been made in HVAC efficiency. For air conditioners, efficiency is measured by a Seasonal Energy Efficiency Ratio (SEER) number. The higher the number, the more efficient the unit is (and usually the more expensive the unit is). Purchase the highest rated unit you can afford.

HVAC Types

Forced Air Furnaces
When it comes to heating, the newest energy efficient forced air furnaces approach the mid 90% range - this means that over 90% of the energy created by the furnace is captured for heating your home. This also means that the exhaust produced is significantly cooler than a traditional furnace - the high efficiency units capture much of the exhaust heat and return it back to help heat your home. High efficiency furnaces can often be vented directly through the wall rather than up a flue through the roof. The cost of a high-efficiency furnace is approximately equal to the cost of a standard furnace plus relining the flue (often a requirement). Gas is significantly more efficient than electricity, though electric furnaces (non-combustion) do not have any venting requirements at all.

Hot Water Heating Systems
If adding central air conditioning is a priority, you will have to make the decision whether to keep your existing hot water system and repair it as required, or to replace it with central heating. The first step in making this decision is verifying the operating condition of your existing system. Some of the key things to check are: the boiler (is the pilot light operational, does it fire properly, is it properly vented), the pump, the pipes (is the system filled properly, are there any leaks, does the insulation contain asbestos), and of course the radiators themselves (are there any leaks, are the valves in working order, are they adequately sized).

All things considered, hot water heat is generally less expensive and more comfortable than forced-air heat. Many people feel that because radiators are designed to heat your rooms through both convection (air movement) and radiation (direct heat), they heat rooms more “evenly”. Also, the interior air in the house is maintained with more humidity. It is important, however, to learn how to maintain your hot water system properly in order to maximize its benefit. An important HVAC investment will be a “radiator key” available for under $2 at many city neighborhood hardware stores. This “key” fits the small valve at the top of each radiator and allows you to release trapped air when filling the system.

If it is in good or repairable condition, I generally recommend keeping the existing hot water heat for general heating needs and adding a forced air system on top for cooling in the summer. For a relatively small cost, your contractor will place an electric heating element in your forced air system as a backup. Removing existing radiators nearly always necessitates patching floors where the pipes enter and often repairing the wall behind the unit.

Multi-Zone HVAC Systems
If you intend to add central air and heat to a building with radiator heat, you will need to find space for the blower unit inside and the condenser outside. In a single-zone system, the blower unit is usually placed in the basement. Some buildings, due to their size or layout, require additional HVAC units to heat and/or cool effectively. Multi-zone systems such as this allow greater temperature control and allow each unit to operate more efficiently. In a three-story home, one unit will typically be located in the basement to serve the first floor, and one unit will be located in the attic to serve the third and second floors.

Radiant Heating
In-floor radiant heating is typically considered as a supplementary system rather than the primary means of providing heat. It consists of a grid of heating elements (electric) or small-diameter tubing (hot water)HVAC Duct running between joists that runs throughout the area to be heated. Though in-floor radiant heating systems can be installed under any type of flooring, they are typically used in areas like bathrooms to heat a cold tile floor and provide continuous, even heat to the room.

Alternative Temperature Control
Alternatives to standard heating and cooling include passive systems such as double-hung windows, shade plantings, and solar heating. Active systems include ceiling fans (a cost effective means of regulating air temperature) and geothermal heat pumps.

HVAC Rough-In

Your HVAC contractor will perform “load” calculations based on the size and layout of rooms, location and size of windows, and the location of the fan and condenser units. These calculations indicate the required capacity of the system and the size of ducts and vents. You can compare the suggested capacities (measured in “tons”) from several contractors. If there are significant disparities, ask them to explain their reasoning. An improperly sized system will cool and heat inefficiently resulting in higher energy costs and more frequent maintenance.

The HVAC rough-in work usually involves installation of the main trunk lines and ductwork for air distribution throughout the house. You will need to have space within the walls for the supply ductwork and the return air – your architect will plan for this in the design stages. Also included in this stage is the installation of flexible duct for bathroom fans and range hoods. Because the HVAC system is large and relatively inflexible this contractor should start work before the others. A “high velocity” system uses smaller, flexible ducts to distribute air. The high velocity vents are generally less visible than the standard floor and wall vents. These systems are generally more expensive.

Your HVAC contractor should be responsible for acquiring all appropriate permits and securing the inspection after work is complete.

Plumbing Rough-In

Your plumber deals with all the PVC (plastic), copper, flexible, and cast iron pipes in your house. This includes the water supply, drains, vent stack, sewer connection, hot water radiators, and natural gas. As with all your other contractors, make sure that your plumber has experience working in renovations, particularly if you are pursuing historic tax credits.

It is important to coordinate between the plumbers and carpenters - there may be unique situations where walls, chases, and soffits must be framed to create space for waste stacks, plumbing traps, and vents.

The rough-in stage involves installation of all pipes up to the location they protrude from the wall. Later, after the drywall and cabinets have been installed, the plumber returns to install the fixtures and connect them to the water system. The major exception to this rule is the bathtub/shower. The tub/showers must be installed in their final location before the rough plumbing inspection, which involves filling and draining the tub. You will have to purchase the tub and shower fixtures, shower valves, and drains in order for the plumber to complete the rough-in.

Electric Rough - Let There Be Light

Many older homes are outfitted with “knob and tube” wiring where individual wires are supported (and kept from touching each other and the building) by ceramic fittings. This method of wiring is not inherently dangerous unless the fittings or wires are damaged - as is often the case during renovation. Knob and tube wiring also has no provision for the “grounding” wire required for three-prong outlets. Today’s technology consists of an insulated cable that contains three or more wires including at least a “hot” wire, a “neutral” wire, and a ground wire. In BX-type cables (armored cable), required in some situations, the wires are contained within a metal sheathing that provides additional protection. This insulated wire is easy to install and provides a high degree of safety. All new wiring must meet the current electrical code.

Installation

A licensed electrician must install all wiring for outlets, fixtures, switches, and appliances. Anyone may install telephone, cable, and structured data lines. You can save some money on electric by running these wires yourself – phone lines may be “chained” together, but each cable and structured data outlet should have a “home run” to the basement where they can be managed individually or hooked into a home automation system.

The rough-in phase for your electrical system includes running all the wiring and installing all the junction boxes necessary to implement your electrical concept plan. The wires will terminate at the breaker box, but will not be made "live" until the electric finish later on in the process.

It is sometimes useful to walk through the building with the electrician who will be performing the installation. This will give you a chance to make any last-minute corrections or additions.

The electric system is the most flexible of the three major systems. While your electrician must follow applicable codes that dictate where wires may run, it is generally possible to get a fixture or outlet pretty much anywhere you want. It is much easier, however, to place fixtures and outlets in frame walls than it is to place them in masonry walls. If you must have an outlet in a masonry wall, the brick has to be chipped out to allow space for the wiring and the outlet or fixture. Then the wall is repaired to hide the wiring. I generally discourage surface-mounted wiring and fixtures, even when allowed by code, unless there is not other alternative.

Safety

Some spaces require specific types of safety features. All outlets near “wet” areas like the kitchen and bathroom must be Ground Fault Circuit Interrupter (GFCI) outlets. A GFCI protected outlet cuts power instantly in the event that a ground fault (for example if you drop your hair dryer into the bathtub) is detected. Also, all outlets in bedrooms must be protected by an “arc-fault” circuit breaker. This special type of breaker helps prevent fires by detecting sparks that can pass between damaged wires within the wall.

Special Cases

If your home is particularly large or unusually shaped, you may want to consider having the electrician install a “sub-panel,” or secondary breaker box. For example, in a three-story house, a sub-panel may be installed in a second floor hallway to serve the second and third floors. Some labor is saved this way because circuits on the upper floors do not have to return all the way to the main box in the basement. It is easier to add additional circuits in the future if need be. Also, if a breaker is tripped, you don’t have to go all the way to the basement to reset it.

Ceiling fans require a different, tougher, ceiling-mounted box than a typical light fixture. Since you can mount a standard light fixture into a ceiling fan box, consider upgrading the mounting in all living spaces even if you don’t intend to have ceiling fans there from the start. That way if you want to add a fan in the future, it will be as easy as replacing the fixture.

The permanent alarm system, if you are purchasing one, should be installed after the general wiring and phone line have been connected.

Windows

Windows are important not just to let light in and keep out the weather, but also as a defining feature of your homes’ style. Windows are categorized by several characteristics: material, number of panes of glass, method of opening, and any unique features. For example a wood, arch-top, 2/2, double-hung window has the following characteristics: (1) the sashes and frame are constructed from wood, (2) the top sash is curved at the top, (3) each sash has two divided panes of glass, and (4) both sashes move up and down.

Repair, Replace, or Replicate

The key decision you will have to make is whether to repair or replace your windows. Historically speaking, repair is generally the preferred method. A tightly sealed, well-installed, high quality storm window installed over your repaired historic wood window will provide an acceptable barrier to the weather. Repairing a historic window may involve replicating deteriorated pieces of the frame or sill, reglazing the sashes, weatherstripping, stripping/painting, and rehanging the counterweights. Reglazing a window and rehanging the weights are skills that are easily learned by a novice. Replicating deteriorated wood pieces requires special tools and skills that may be better left to professionals or those with significant experience.

In the event that the sashes are beyond repair but the frames are still in good condition, a millwork shop may be able to create replacement sashes for much less cost than a full replacement window. They may also be able to re-mill your existing sashes to accept insulated glass if you want to upgrade the glazing.

Window Replacement

If you decide to replace the windows, you will be faced with a myriad of decisions regarding the cost, style, construction, and efficiency of the replacement windows. Within the bounds of this overview, only some of these decisions will be discussed. The four major types of modern window construction are wood, aluminum, clad, and vinyl.

  • Wood windows are usually the most expensive. The window frame and sash are made of wood. Most often the wood used to build today's windows is not as high quality as that used when your home was built. In addition, the actual windows and mechanisms themselves are constructed differently. However, it is typically easier to get a wood replacement window that closely matches your existing windows than with other materials.

  • Aluminum windows are constructed of extruded aluminum, usually with a factory finish selected from a small set of colors. Aluminum conducts heat, so it is important to have what is called a "thermal break" or gasket that prevents transfer of heat through the window frame. Materials and methods are advancing to the point where many historic window profiles can be created.
  • Clad windows are typically wood with an aluminum "skin" on the exterior. The idea behind clad windows is to minimize required exterior maintenance (painting).
  • Vinyl windows are the least expensive window option, but you get what you pay for. Vinyl windows come in a limited color palate will not last as long as well cared-for aluminum or wood windows.

Almost all new single-hung and double-hung windows are friction mounted – very few use a counterweight system. Of the four types, wood and clad are typically the most expensive but also the most historically accurate. Some aluminum windows can also replicate the general look of some historic windows, but the standard color selection is more limited and arch-tops may not be possible. Vinyl windows are the least expensive, the least historically accurate, and will generally have a shorter lifecycle (regardless of what the salesperson claims).

Some rules to follow:

  1. Square pegs don't fit into round holes - never replace an arch-top window with a square top window. They look ridiculous and diminish property values.

  2. If your house is located in a local historic district, never replace windows without the appropriate approvals.
  3. Never install an undersized replacement window just because you were able to get a "deal". The sizes and shapes of your windows are a key component to the historic character of your home. In some cases it may be desirable to raise the sill (do so in a sensitive manner) in order to install new cabinets or make some other architectural change.
  4. Match the muntin patterns of your existing windows.
  5. Install shutters only in historically appropriate locations (fasteners, hinges, and different brick color may indicate that there were previously shutters on your house). If you do, make sure they are appropriately sized.
  6. Storm window size and shape should reflect the window behind. Never install two storm windows over a larger double hung window - it changes the character of the elevation.

If your home is located in a local historic district, make sure you follow the City's requirements for permitting exterior work!

Energy Efficiency

A window’s energy efficiency is difficult to determine because the window is only one part of the entire “building envelope” system to keep out the elements. Window salespeople will, of course, try to sell you to a more efficient, and more expensive model. Keep in mind, however, that even the most efficient window will be ineffective if air can infiltrate through other openings. Look at your building as a system that is only as effective as its weakest component. Windows are one case where you have to balance the sometimes-conflicting goals of cost, efficiency, and style.

Drywall Installation and Taping

Many of the Des Moines’ historic homes were built with plastered interior walls. Because it is so labor-intensive (and therefore expensive), plaster is not considered a standard building practice in today’s construction industry. A plaster wall is constructed in several stages. First, small strips of wood called lath are nailed across the studs (walls) and the bottoms of floor joists and rafters (ceilings). Plaster is typically applied onto the lath in three layers. The first layer is the thickest and applied directly to the lath. As it is applied to the wall or ceiling, some of the plaster gets pressed through the horizontal spaces between the lath strips. These “keys” harden and became the supports that hold the plaster to the wall or ceiling. The second layer of plaster is much thinner and helps level the surface. The final layer consists of a mixture of lime and plaster, or plain lime putty, and is applied to a thickness of approximately 1/8” before being floated to a near-flat surface.

You will find it is very difficult to remove small areas of plaster without damaging the surrounding area – if the “keys” that hold the plaster to the lath fall off, the plaster itself becomes very weak. It is likely that during your renovation, you will either completely remove the plaster or significantly damage areas of plaster in order to update the electric, plumbing, and HAVC systems.

Drywall

In these areas, you will likely replace the plaster you remove with drywall. Drywall is a “sandwich” of gypsum between two layers of paper backing. It is fabricated in sheets that come in a range of sizes 48” wide by 8 to 12 feet long. Larger drywall suppliers have a truck with a crane and will, for a fee, hoist the drywall into second and third-floor windows and distribute it throughout the rooms. Particularly in buildings with tight stairways or small hallways, it may be impossible to carry a full sheet between floors, so this service can be invaluable.

Sometimes a vapor barrier is installed between the insulation and the drywall. A vapor barrier is a plastic sheeting that prevents air and moisture infiltration into the building and can improve its energy efficiency. A vapor barrier must be installed on the “warm” side of the insulation or moisture can condense inside the wall and cause significant damage.

Hanging and Taping

A finished drywall surface happens in two stages: hanging and taping. Hanging drywall takes some muscle, but with the right tools and some persistence, the skills are relatively easy to acquire. If you have never hung drywall, ask someone with experience to help you for a few hours until you understand the process. Most general “how-to” books contain sections on hanging drywall.

Essentially, large sheets of drywall are screwed or nailed to the studs and joists to create a flat surface. Screws will create a stronger connection than nails and will result in fewer “pops” where the connector becomes visible as the house shifts or settles.

Tools required for installing drywall include:

  • Cordless drill (with spare battery and charger)

  • Utility knife (with plenty of spare blades)
  • Drywall square (a four foot "T" shaped tool)
  • Keyhole saw
  • Tape measure
  • Chalk line, and
  • Carpenter's pencils

A drywall lift is a hand-cranked lifting platform for holding sheets of drywall when hanging the ceiling. Using a lift makes the job manageable for even a single person who has the strength to move a whole sheet onto the lift.

It is generally best practice to install the largest piece of drywall that will fit in a space, minimizing the number of joints. It is also best practice to install full sheets of drywall perpendicular to the studs or joists in order to minimize “pops” and cracks. In cases where the sheets must be cut, it is scored through the paper on one side with a utility knife and snapped by bending. Cutting the paper on the opposite side then separates the piece.

Managing Drywall Installation

If you hire people to hang and tape the drywall, there are some things to look for before releasing their final payment. The primary issue is quality - to check the quality of the taping, take a high-powered construction lamp (halogen) and place it near to the wall, shining it each direction. Rough areas, bumps, and depressions that should be dealt with will cast shadows along the wall. Also veryify that none of the electric boxes have been covered up. If any are covered up, the electrician will likely forget to install the appropriate fixture. For example, you don't want to get caught in a situation where your building inspector is performing the final inspection and notes a "missing" smoke detector. The drywall installer can locate the covered electric boxes using a long level and noting any "bulges" in the ceiling (properly installed boxes protrude beyond the stud or joist).

Fixtures and Finishes

Up to this point, much of the work in your home has been occurring “behind the scenes” – it has now been covered up by the drywall. The finishes include everything from the drywall out.

The finish decisions you make will drastically affect the look, feel, livability, and budget of your renovation project. Even though fixture and finish installation is one of the last stages, you should begin selecting the finishes early in the process for two primary reasons. First, most finishes are available in a broad range of quality and cost. Unless you have a bottomless wallet, you will be forced to make some tough decisions on where you want higher quality finishes and where you can live with more moderate selections. If towards the end of construction, you have money left over in your contingency fund, consider putting it towards higher-end finishes. The second reason to begin selecting finishes early in the process is that many products must be custom fabricated and/or be shipped from far-away locations. Selecting the finishes early ensures that they will be available when you need them installed. Late arrivals can initiate a domino effect and negatively impact the remaining schedule of the project.

Allowances

If you are working with a general contractor, you may have an “allowance” for your various finish types. An allowance is the contractor’s recognition that you will have decisions to make through the course of the project. For example, consider that your architectural drawings specify “wood” flooring in the dining room. This gives the contractor a ballpark idea of what you are intending to do. When putting together the bid, he or she figures that there is 150 square feet of floor, and oak costs about $6 per square foot totaling $900. This will be the base price in the estimate and you would get a flooring allowance of $900 to apply to any flooring you select. If you decide to install a walnut parquet floor that costs $20 per square foot, you would pay the difference. Because prices vary so much, the allowance method can apply to any of the finishes.

The contractor may also simply exclude some of the finish materials from his or her bid. In this case you would be required to purchase the product on your own and have it on hand when they are ready to install. Some of the finishes you may have to select may include:

  • Flooring

  • Kitchen cabinets, bathroom vanities, and drawer pulls
  • Plumbing fixtures and faucets
  • Specialty items such as mailboxes, toilet paper holders, and towel bars
  • Flooring (vinyl, wood, tile, etc)
  • Paint colors
  • Light fixtures and ceiling fans
  • Countertops
  • Architectural woodwork such as window trim, base molding, fireplace surrounds, etc., and
  • Appliances

Subcontractors

At this stage, your plumbing, HVAC, and electrical subcontractors will come back to install the fixtures and complete their work.

The HVAC subcontractor will install all of the vent covers and balance the system. The electrician will make the final connections to power up all of the circuits and install all of the electrical fixtures. The plumber will install all of the plumbing fixtures (except for the tub which had to be installed earlier in the process).

Carpenters are typically responsible for installing the cabinetry.

Systems Finish

Once the drywall is installed, taped, and painted, the cabinets placed, tile laid, and all the fixtures are on site the systems finishing stage begins. You will call back your electrician, plumber, and HVAC contractor to install the final pieces of each trade and complete the contracted work. You should hold back a reasonable portion of the contract payment until the finish work is completed to your satisfaction.

The HVAC finish work includes placing the fan units and condensers, charging the air conditioner if required, and placing the vent covers.

When you have received all your new electric fixtures, distribute them throughout the house, label where they are to be mounted, and call your electrician to return. At the end of the electric rough-in, your electrician likely left the home runs dangling, unconnected, at the breaker box. The electric finish consists of installing the appropriate sized circuit breakers, connecting all the wires, installing your fixtures, and powering the system. The electrician will also install the thermostats and power the condensers, so make sure that the heating and cooling units are in place.

Your plumber will return to install the plumbing fixtures after the cabinets and counters are in place. Verify that all the fixtures work, drain properly, and that valves don’t stick before releasing the final payment. The plumber will also connect the overflow pan for any HVAC units or washing machines on the second and third floors.

Landscaping and Sitework

During construction it is likely that the lawn will sustain significant damage from building material storage, dumpsters, machinery, utility trenching, and general use. Once the finish carpentry begins, however, most of the heavy yard use is over – you can begin to clean up debris and plan any landscaping you want done.

Your landscaping plan may be as simple as removing overgrown bushes and planting grass; or as complicated as installing a sprinkler system, retaining walls, and hiring a landscape designer to create a backyard oasis. Either direction you choose, landscaping should be one of the last activities in your renovation process. This ensures that your contractor will not accidentally damage your new plants and lawn.

Project Close-Out

Congratulations! You are finally ready to move in.

Well, not quite yet. Before you start moving your belongings in, and certainly before you issue the last payment to your contractor, you need to perform a detailed walkthrough and prepare a "punchlist" for your contractor. Renovation is a complex business and there are many opportunities for things to get overlooked, particularly in the final stages as the pressure mounts to complete your project. The punchlist may be your last opportunity to get timely work out of your contractor - once you have approved the final payment and received the final lien waiver, your options become much more restricted.

A punchlist is simply a list of items (these items must be either specifically included or reasonably implied in the contract, of course) that the contractor needs to complete prior to receiving the final payment. You may want to prepare the punchlist with the assistance of your contractor. That way, you can ask questions and make sure that you are on the same page.

Some things you might want to pay particular attention to as you do your punchlist walkthrough include:

  • Switches and lights - Flip every switch and make sure it is working and correctly installed

  • Outlets - Purchase a cheap tester (you could even use a night light) and make sure that every outlet works.
  • Faucets - Let the tap run until it gets hot (test the cold too)- as the water is warming up, look underneath to make sure there are no visible leaks in the drain
  • Drywall - Examine every wall and make sure there are not "nail pops", cracks, or unfinished corners
  • Paint - Examine every wall and ceiling to look for areas of poor coverage or obvious mistakes
  • Fixtures - Make sure plumbing fixtures are caulked where required, flush every toilet, turn on the shower, etc.
  • Cleaning - The contractor should turn over a clean building, and all construction waste should be removed (you may ask for leftover paint, carpet trimmings, etc.)
  • HVAC - turn on all HVAC equipment (heat and cool) to test operation - make sure all required filters are installed
  • Trim - Look for missing pieces of trim or base shoe, poor corners, and other obvious flaws

If the contractor is not present when you create the punchlist, give him or her a copy and discuss it in person. You may withhold a portion of the final payment until the punchlist items are corrected.

Your last step is to obtain the final inspection and get a copy of your certificate of occupancy if required. In addition to verifying the permitted work was performed and that the building meets minimum code requirements, your inspector will measure the rooms and make any changes to the city’s database. If anything does not meet building code or applicable city ordinances, you may be cited and required to make additional repairs within an acceptable time frame.

More to Come...

The Renovation Guide is under construction. New article will be added on a regular basis over the next month or so until it is complete. Please check back often - the right side bar on the front page lists the 10 most recent articles and updates.

Thanks for your patience as content is developed!